التحليل الكمي للمخاطر Quantitative Risk

تقليص
X
 
  • تصفية - فلترة
  • الوقت
  • عرض
إلغاء تحديد الكل
مشاركات جديدة

  • التحليل الكمي للمخاطر Quantitative Risk




    Quantitative risk analysis is a numerical estimate of the overall effect of the risk on the objectives of the project, such as the cost and schedule objectives. The results provide insight into the likelihood of the success of the project and are used to develop contingency reserves.
    A quantitative analysis
    Creates realistic and achievable targets for costs, schedule, or scope.
    Quantifies the potential outcomes of the project and assesses the probability of achieving specific objectives for the project.
    Provides a quantitative approach to decision-making where there is uncertainty
    To conduct a quantitative risk analysis, high-quality data, a well-developed project model, and a priority list of project risks will be required (usually from conducting a qualitative risk analysis).
    There are three risk elements that concern project management:
    Schedule – Will the project be completed within the planned schedule?
    Cost – Will the project be completed within the budget allocated?
    Performance – Will the output of the project meet the business and technical objectives of the project?
    Where possible, these risks should be quantified to allow the project team to develop effective risk mitigation strategies or to include appropriate contingencies in the project estimate.
    How is Quantitative Risk Assessment Done?


    The risks are identified and put on a list. Risks must be prioritized from this list, and then fed into a Risk Register. Then, these risks are ranked according to their severity and impact level by using distributions of probability to calculate the impact and probability of the risk. It also takes advantage of constraints such as schedule, cost estimates, and other resources.
    Why to Perform a Quantitative Risk Analysis?
    Better Overall Project Risk Analysis: In the qualitative risk analysis individual risks are assessed. But the quantitative analysis enables us to assess the overall project risk from the individual risks plus other risk sources.
    Better Business Decisions: Business decisions are rarely made with all the information or data that we want. Quantitative risk analysis provides more objective information and data for more critical decisions than qualitative analysis. Keep in mind that while quantitative analysis is more objective, it is still an estimate. Wise project managers are considering other factors in the decision-making process.
    Better Estimates: The project manager estimated the duration of the project to be eight months at a cost of $400,000. The project actually lasted twelve months, costing $480,000. What happened? The project manager conducted a Work Breakdown (WBS) structure and estimated the work. However, the project manager failed to consider the potential impact on schedule and budget of the risks (good and bad).
    When to Perform Quantitative Risk Analysis?


    Firstly, we ‘re identifying risks. Then, we can qualitatively and quantitatively assess the risks. Consider using quantitative analysis of risks to:
    Projects where upper management wants more detail on the probability that the project will be completed on schedule and within budget.
    Projects requiring a contingency reserve for the schedule and budget.
    Quantitative Risk Assessment Tools and Techniques


    Quantitative Risk Analysis tools and techniques shall include but not limited to:
    Three-Point Estimate: A technique that uses the optimistic, most likely, and pessimistic values to make the best estimate possible.
    Decision Tree Analysis: A diagram showing the implications of choosing one or the other alternatives. The decision tree is a diagram of the decision Consideration and implications of choosing one or the other of the alternatives available.
    Monte Carlo Analysis: A technique that uses optimistic, most likely, and pessimistic estimates to determine the overall cost of the project and the project completion dates. For example, we could estimate the probability of completing a project at a cost of $20 million. Or what a company wanted to be an 80% probability of achieving its cost objectives. What is the cost of achieving 80%?
    Expected Monetary Value (EMV): Method used to establish contingency reserves for the budget and schedule of the project.
    Fault Tree Analysis (FMEA): Analysis of a structured diagram that identifies elements that may cause a system failure.
    Sensitivity Analysis: a technique used to determine which risks have the greatest impact on a project.
    Quantitative Risk Analysis Example


    Let’s look at the following simple example of Expected Monetary Value (EMV):
    Keep in mind that risks involve both threats and opportunities. Threats have an adverse cost impact. Opportunities are benefits that reduce costs.
    Expected monetary value = probability x impact.
    اضغط على الصورة لعرض أكبر  الاسم: evm-300x108.png الحجم: 29.8 كيلوبايت رقم التعريف: 225287

    Note that we subtracted the benefit of the Opportunity from the EMV. The Total EVM value represents the project risk exposure and the amount of our Contingency Reserve

    اقرا ايضا

    إدارة المخاطر Risk Management
    . التحضير لشهادة pmp من كتاب pmbok 6
    التعديل الأخير تم بواسطة HaMooooDi; الساعة 02-17-2024, 07:35 PM.

المواضيع ذات الصلة

تقليص

المواضيع إحصائيات آخر مشاركة
أنشئ بواسطة HaMooooDi, 03-31-2024, 02:15 AM
ردود 0
5 مشاهدات
0 معجبون
آخر مشاركة HaMooooDi
بواسطة HaMooooDi
 
أنشئ بواسطة HaMooooDi, 03-17-2024, 09:51 PM
ردود 0
17 مشاهدات
0 معجبون
آخر مشاركة HaMooooDi
بواسطة HaMooooDi
 
أنشئ بواسطة HaMooooDi, 03-16-2024, 05:22 PM
استجابة 1
21 مشاهدات
0 معجبون
آخر مشاركة HaMooooDi
بواسطة HaMooooDi
 
أنشئ بواسطة HaMooooDi, 03-11-2024, 01:49 PM
استجابة 1
21 مشاهدات
0 معجبون
آخر مشاركة HaMooooDi
بواسطة HaMooooDi
 
أنشئ بواسطة HaMooooDi, 01-28-2024, 02:35 AM
ردود 0
11 مشاهدات
0 معجبون
آخر مشاركة HaMooooDi
بواسطة HaMooooDi
 
يعمل...
X